RIO TINTO
Marandoo HDD Dewatering
PROJECT TIMEFRAME | February – April 2024
PROJECT LOCATION | Marandoo
Project Scope
Earthworks
Project Execution
- Services provided: Earthworks, site preparation, risk assessment, traffic management, compaction testing, and documentation.
- Process:
- Risk assessment workshop
- Permit acquisition
- Site mobilization and setup
- Burrow pit establishment
- Material stockpiling and conditioning
- Traffic management and survey control
- Vegetation and topsoil removal
- Foundation compaction
- Fill material hauling and compaction
- Roadbase and 20mm material installation
- Compaction testing and survey
- Site tidying and drainage
- Documentation completion
- Timeline: Project completed in 11 weeks, meeting the client’s timeframe.
Challenges and Solutions
- Challenge: Adverse weather conditions.
- Solution: Increased resources and adjusted timelines.
Core Values in Action
- Teamwork: Collaborative effort to achieve project goals efficiently and safely.
Overall, this earthworks project was successfully completed on time, within the client’s timeframe, and with a high level of quality and safety. The team effectively navigated challenges posed by adverse weather conditions, demonstrating their commitment to teamwork and problem-solving.