SHIRE OF ASHBURTON

Caravan Dump Point

PROJECT TIMEFRAME | June 2023
PROJECT LOCATION | Onslow

Project Scope
Installation of a caravan dump point including concrete and plumbing works.

Project Execution

  • Services provided: Installation of caravan dump point, concrete works, plumbing, bollards, and signage.
  • Process: Excavation, installation of dump point, concrete pouring, plumbing for additional taps, and installation of bollards and signage.
  • Timeline: Project completed in 2 weeks, meeting the client’s timeframe.

Challenges and Solutions

  • Challenge: Unexpected underground water leak discovered during excavation.
  • Solution: Leak repaired at no additional cost to the client.

Core Values in Action

  • Safety: Prioritised through area control and temporary fencing to protect the public.
  • People: Used dual-trade personnel for efficient completion of tasks.
  • Exceptional Skill: Demonstrated high-quality concrete finishing.
  • Exemplary Service: Proactive job planning due to remote location.

Overall, this project was successfully completed on time, within budget, and with a high level of quality and safety.