SHIRE OF ASHBURTON
Caravan Dump Point
PROJECT TIMEFRAME | June 2023
PROJECT LOCATION | Onslow
Project Scope
Installation of a caravan dump point including concrete and plumbing works.
Project Execution
- Services provided: Installation of caravan dump point, concrete works, plumbing, bollards, and signage.
- Process: Excavation, installation of dump point, concrete pouring, plumbing for additional taps, and installation of bollards and signage.
- Timeline: Project completed in 2 weeks, meeting the client’s timeframe.
Challenges and Solutions
- Challenge: Unexpected underground water leak discovered during excavation.
- Solution: Leak repaired at no additional cost to the client.
Core Values in Action
- Safety: Prioritised through area control and temporary fencing to protect the public.
- People: Used dual-trade personnel for efficient completion of tasks.
- Exceptional Skill: Demonstrated high-quality concrete finishing.
- Exemplary Service: Proactive job planning due to remote location.
Overall, this project was successfully completed on time, within budget, and with a high level of quality and safety.