MEA Brockman 2 GTU Upgrades

PROJECT TIMEFRAME | August 2023 – October 2023
PROJECT LOCATION | The Pilbara

Project Scope
Minor Earthworks, Concreting & Grouting

Project Execution

  • Site Preparation:
    • Leveling the area and installing a spoon drain.
    • Importing and compacting 60 tonnes of roadbase material for site facilities.
  • Excavation and Utilities:
    • Hydro-excavating to locate underground services.
    • Excavating existing surface and removing to spoil.
    • Compacting the foundation and pouring concrete blinding.
  • Foundation and Pedestal Installation:
    • Installing new footings with steel reinforcement.
    • Installing new pedestals with steel reinforcement, anchor bolts, and earthing bonds.
    • Removing formwork, backfilling, and compacting with Type A – Select Fill material.
  • Finishing Touches:
    • Supplying and installing bollards.
    • Scabbling concrete for grouting.
    • Tidying the work area and ensuring proper drainage.

Project Timeline

  • Duration: 3 months
  • Client Timeframe Met: Yes

Challenges and Solutions

  • Challenge: Working between shutdowns and timelines
  • Solution: NWMC adjusted crew size to meet project deadlines.

Core Values in Action

  • Exemplary Service: NWMC collaborated closely with the client to plan access to work areas, ensuring efficiency for all teams onsite. This proactive approach not only facilitated smooth operations but also demonstrated our commitment to providing exemplary service by prioritising effective teamwork and client satisfaction.

Overall, the project was successfully completed within the specified timeframe, despite challenges. NWMC’s core values of collaboration and adaptability played a crucial role in overcoming obstacles and delivering a high-quality result.